Dragon Link - Production Run #1

Posted: Wed 27 May 27 2009 4:03 pm
by Daniel Wee
PCBCART has sent out the PCB (27 May 2009) so I expect to get them in about 10-days or so.
RF Modules will be ready for delivery about mid-June, so about 2 to 3 weeks from now.

Daniel

Re: Dragon Link - Production Run #1

Posted: Thu 28 May 28 2009 1:12 pm
by John Lee
35 Teko cases just shipped out of Pennsylvania, USA today (May 27th, 2009) and on it's way to Duncan, CND.

Re: Dragon Link - Production Run #1

Posted: Sat 30 May 30 2009 11:49 am
by Daniel Wee
Bought 90% of all the needed components and parts.

PCB arrived.

Daniel

Re: Dragon Link - Production Run #1

Posted: Tue 02 Jun 02 2009 6:08 pm
by Daniel Wee
Some assembly underway now with components on hand:-
IMG_0380a.JPG
IMG_0380a.JPG (92.13 KiB) Viewed 24920 times
IMG_0379a.JPG
IMG_0379a.JPG (104.43 KiB) Viewed 24920 times
Daniel

Re: Dragon Link - Production Run #1

Posted: Sat 06 Jun 06 2009 12:28 pm
by Daniel Wee
Had to cancel a Mouser order (#2) and re-order from Farnell. Still waiting for resonators.

Daniel

Re: Dragon Link - Production Run #1

Posted: Sat 06 Jun 06 2009 9:22 pm
by Daniel Wee
25 TX and 30 RX boards done, 5 board could go either way. Most still awaiting resonators - probably next week:-
IMG_0392a.JPG
IMG_0392a.JPG (121.13 KiB) Viewed 24914 times
25 PSU's done - waiting to be wired up:-
IMG_0394a.JPG
IMG_0394a.JPG (90.31 KiB) Viewed 24915 times
Wires getting prepared (at 5 bucks an hour):-
IMG_0396a.JPG
IMG_0396a.JPG (63.67 KiB) Viewed 24914 times
Daniel

Re: Dragon Link - Production Run #1

Posted: Tue 16 Jun 16 2009 8:22 pm
by Daniel Wee
Got news that the second board is in the mail and should arrive in about a week - or maybe this Friday (but I'm not around by then).

Daniel

Re: Dragon Link - Production Run #1

Posted: Wed 17 Jun 17 2009 10:54 am
by John Lee
32 Teko cases (2 days ago) completed and ready for Daniel to send off the rest when he is ready.
P1020460.JPG
P1020460.JPG (364.18 KiB) Viewed 24908 times
P1020466.JPG
P1020466.JPG (421.54 KiB) Viewed 24908 times
P1020463.JPG
P1020463.JPG (506.25 KiB) Viewed 24908 times
P1020469.JPG
P1020469.JPG (454.13 KiB) Viewed 24908 times

Re: Dragon Link - Production Run #1

Posted: Sat 04 Jul 04 2009 12:48 am
by Daniel Wee
20 Receivers assembled, fused and programmed. They just need to be calibrated and tested, then have heatshrinking applied.
IMG_0553a.JPG
IMG_0553a.JPG (83.19 KiB) Viewed 24899 times
Daniel

Re: Dragon Link - Production Run #1

Posted: Mon 06 Jul 06 2009 10:21 pm
by Daniel Wee
My half of the TX boards all done:-
IMG_0615a.JPG
IMG_0615a.JPG (73.85 KiB) Viewed 24893 times
Daniel